An infill or gap site, in Northern Ireland countryside planning, is a small gap in an otherwise substantial and continuously built-up road frontage that is big enough for no more than two houses. Under Policy CTY 8 of PPS 21, a new building that creates or adds to a ribbon of development will normally be refused, but there is an exception for this kind of small gap. It is one of the most misunderstood countryside policies. A space between two houses is not automatically an infill site, and many apparent gaps do not qualify.
This guide explains how the policy reads, how councils tend to apply it, and what to check before you buy or apply. It is general information, not advice on a particular site.
Which policy applies?
PPS 21 is still the operational countryside policy in councils that have not yet adopted a Plan Strategy. At the time of writing (November 2026), six councils have adopted one: Belfast, Fermanagh and Omagh, Lisburn and Castlereagh, Mid and East Antrim, Antrim and Newtownabbey, and Derry City and Strabane. Their infill policies are similar in purpose but are not word-for-word copies of CTY 8, so read the council’s own policy for sites in those areas. Our article on whether PPS 21 still applies explains the difference.
Start with the rule: ribbon development is refused
CTY 8 begins with a refusal: planning permission will be refused for a building which creates or adds to a ribbon of development. PPS 21 explains that ribbon development harms the character, appearance and amenity of the countryside, can make access to farmland difficult and can cause road safety problems.
A ribbon does not have to be neat. PPS 21 says buildings sited back, staggered or at angles, with gaps between them, can still be a ribbon if they have a common frontage or are visually linked. A road frontage also includes a footpath or a private lane.
The infill exception, test by test
The exception allows the development of a small gap site where all of the following apply.
A substantial and continuously built-up frontage
The policy says a substantial and built-up frontage includes a line of three or more buildings along a road frontage without accompanying development to the rear. In practice, councils look at the buildings that actually front onto the same road or lane, and whether together they read as a continuous built-up frontage.
Points that often cause debate include:
- whether a building has frontage to the road, or sits behind another building or is set well back;
- whether outbuildings, sheds or garages are counted; and
- whether the frontage is broken by a laneway, a large field or a change in direction of the road.
A small gap, sufficient for up to two houses
The gap must be small, and sufficient only to accommodate up to a maximum of two houses. Councils usually judge this by comparing the gap with the plot widths along the rest of the frontage. A gap that could fit three or more plots of the prevailing size is unlikely to qualify, even if only one or two houses are proposed.
Respecting the existing development pattern
The new house or houses must respect the existing pattern along the frontage in terms of size, scale, siting and plot size. PPS 21 says it will not be enough to show that two houses could physically fit. The design must take full account of the pattern of development and integrate the new buildings.
Meeting other planning and environmental requirements
The usual countryside tests still apply: integration and design (CTY 13), rural character (CTY 14), safe access with appropriate visibility splays, and sewage disposal where there is no mains connection (CTY 16).
Why many gaps do not qualify
PPS 21 recognises that many countryside frontages have gaps between houses that provide relief and visual breaks, and that help maintain rural character. Those gaps are meant to stay open. That is why the gap must be small, and why the frontage on each side must be substantial and continuous.
Common problems include:
- only two buildings fronting the road, so the frontage is not “substantial”;
- a gap that is wider than the typical plots along the road;
- buildings that do not share a common frontage, for example because one is on a different road or down a long lane;
- a gap that forms an important visual break in an otherwise rural stretch of road; and
- a site that would extend the end of a ribbon rather than fill a gap within it.
Infill is different from a cluster
A gap site is about a line of development along a road. A dwelling in an existing cluster, under Policy CTY 2a, is about a group of buildings around a focal point or crossroads. The tests are different. Our article on building in an existing cluster explains the cluster policy.
What to check before buying a gap site
- Count the buildings with frontage to the same road or lane on each side of the gap.
- Measure the gap and compare it with the plot widths along the frontage.
- Check the planning history of the site and the neighbouring plots, including any refusals.
- Check whether the visibility splays can be provided on land you will control.
- Make any offer subject to planning permission.
Our guide to buying a home, site or farm sets out the wider checks.
Free guide: Download our free 10-page guide, Infill and Gap Sites in the Northern Ireland Countryside, with the CTY 8 tests, how to measure a gap and frontage, which councils use their own Plan Strategy, and a tick-box site checklist. No email or sign-up needed.
How we can help
Our team carries out a desktop and site review of the frontage, measures plots, checks the planning history and gives a clear view of whether CTY 8, or the council’s equivalent policy, is realistically met. If it is not, we will tell you before you commit. See our infill and gap sites service and our wider guide to planning permission for a house in the countryside.
Frequently asked questions
How many houses make a built-up frontage?
Under CTY 8, a substantial and built-up frontage includes a line of three or more buildings along a road frontage without accompanying development to the rear. Whether a particular group qualifies is a judgement for the council.
How big can an infill gap be?
The policy does not set a figure in metres. The gap must be small and sufficient only for up to two houses, and the new plots must respect the size, scale, siting and plot size of the existing frontage.
Can I infill a gap on a private lane?
Yes, potentially. PPS 21 says a road frontage includes a footpath or private lane, so the same tests are applied to buildings along a lane.
Do farm sheds count as buildings for infill?
Sometimes. The policy refers to buildings, not only houses, but councils look closely at whether each building has a genuine frontage and contributes to a continuous built-up frontage.
Talk to us about a gap site