Outline planning permission establishes whether, in principle, a building can be built on a particular site, while leaving some or all of the detail to be approved later. In Northern Ireland, those later details are called reserved matters: siting, design, external appearance, means of access and landscaping. Once outline permission is granted, an application for approval of the reserved matters must normally be made within three years. No building work can start on the strength of an outline permission alone.
Outline is particularly common for new houses in the countryside, where the main question is often whether a house is acceptable on the site at all. This guide explains how it works, its advantages and limits, and when a full application may be the better choice. It is general information, not advice on a particular site.
The legal framework
Outline permission is defined in section 62 of the Planning Act (Northern Ireland) 2011 as permission granted conditional on the later approval of the particulars of the proposed development, the “reserved matters”. The Planning (General Development Procedure) Order (Northern Ireland) 2015 defines reserved matters as any of the following where details have not been given in the application:
- siting;
- design;
- external appearance;
- means of access; and
- the landscaping of the site.
An outline application can include details of some of these, with the rest reserved. For example, a countryside application may fix the site and access in outline and leave design and landscaping for later.
When can the council refuse to deal with it in outline?
Article 4 of the 2015 Order allows the council, where it considers that the application ought not to be considered separately from all or any of the reserved matters, to tell the applicant that it cannot determine the application unless further details are submitted. In practice, councils may ask for more information where the impact on a sensitive landscape, a conservation area, a listed building or neighbouring homes cannot be judged without it.
Outline applications are for new buildings. A change of use or a householder extension is normally made as a full application.
Outline versus full planning permission
| Outline | Full | |
|---|---|---|
| What is decided | The principle, plus any details included | The whole proposal, in detail |
| Can you start work? | No, reserved matters must be approved first | Yes, once pre-commencement conditions are met |
| Typical drawings | Site location plan, often an indicative layout | Full plans, elevations and site layout |
| Time limits (default) | Reserved matters within 3 years; start by the later of 5 years from outline or 2 years from final approval of reserved matters | Start within 5 years |
Why choose outline?
- Testing the principle first. For a countryside site, the key question is often whether a policy route exists, such as a farm dwelling, a replacement dwelling or an infill site. Outline lets the council decide that before you invest in detailed design.
- Selling or buying a site. A site with outline permission can be easier to sell, and a buyer can then design their own house through reserved matters.
- Spreading cost. Detailed design, survey work and some technical reports can wait until the principle is established.
The limits of outline
- You cannot build on an outline permission. Reserved matters must be approved first, and any pre-commencement conditions dealt with.
- Conditions can be restrictive. Countryside outline permissions often carry conditions on ridge height, the siting area, retention of hedges and the access. Those conditions shape the house that can be built later.
- Time limits are tighter than they look. The three-year reserved matters deadline is the one most often missed.
- Two stages. Outline followed by reserved matters means two separate applications, which adds time to the overall programme.
- Some issues are better resolved up front. On sensitive sites, a full application can give more certainty because the council judges the actual design.
Time limits for outline permission
Under section 62 of the 2011 Act, unless the council sets different periods:
- an application for approval of reserved matters must be made within three years of the outline grant; and
- development must begin by the later of five years from the outline grant or two years from the final approval of the reserved matters.
Under section 63, a reserved matters application made after the deadline is treated as not made in accordance with the permission. Our guide to how long planning permission lasts in Northern Ireland covers time limits and renewals in more detail.
Reserved matters: what to expect
A reserved matters application must be consistent with the outline permission and its conditions. If the conditions fix the siting area, a ridge height or the access position, the detailed design has to fit within them. A design that departs significantly from the outline may need a fresh full application instead.
The reserved matters application usually includes full plans and elevations, a site layout showing the access and visibility splays, a landscaping scheme, and any details required by conditions.
Buying a site with outline permission
Before buying, check:
- the date of the grant and the reserved matters deadline;
- every condition, especially those on siting, height, access, landscaping and occupancy;
- whether the visibility splays fall on land included in the sale; and
- whether any agricultural or other occupancy restriction applies.
Our free guide to buying a home, site or farm sets out the wider checks.
Frequently asked questions
What does outline planning permission mean?
It means the council has accepted the principle of a building on the site, subject to later approval of reserved matters: siting, design, external appearance, means of access and landscaping, as applicable.
Can I start building with outline planning permission?
No. The reserved matters must be approved first, and any conditions that must be met before work starts must be discharged.
How long does outline planning permission last in NI?
By default, reserved matters must be applied for within three years, and development must begin by the later of five years from the outline grant or two years from final approval of the reserved matters. The council can set different periods.
Is outline or full permission better for a countryside house?
It depends on the site. Outline is useful for testing the principle. Full permission can give more certainty on sensitive sites. We advise on this as part of a site appraisal.
How we can help
Our team can advise whether outline or full is the right approach for your site, prepare and manage the application, and handle reserved matters and conditions. Call us on 028 9591 6888 or contact us online. See also our planning applications and site appraisals services.
Get planning advice
Send the site address and a line about your plans. A member of our planning team will reply, usually the same working day.