Belfast City Council planning officers have said they will present a 556-unit purpose-built student accommodation scheme, on the site of the former Wellington Park Hotel and the Botanic Inn, to the December Planning Committee with a recommendation to refuse. No decision has been made. As at 24 November 2026 the applications remained live on the NI Planning Register, and the December committee agenda had not been published.
The proposal
The site is the Inn Belfast Hotel (former Wellington Park Hotel) and the Botanic Inn, at 21–27 Malone Road and 6 Wellington Park, Belfast, BT9 6RU. It extends to 0.7 hectares and lies in the Malone Conservation Area. The applicant on the register is Graham Investment Projects, and the agent is Turley. The Irish News has reported a joint venture with the Mooney Hotel Group, which is not named on the Planning Register or the application forms.
Three linked applications are under consideration:
- LA04/2026/1538/F (full planning permission). The registered description is: “Demolition of the existing hotel and public house and erection of a four to six-storey Purpose Built Managed Student Accommodation (PBMSA), with additional use of the accommodation outside term time, comprising 556 no. units, ground-floor retail units, communal facilities, internal and external communal amenity space and ancillary accommodation.”
- LA04/2026/1539/LBC (listed building consent), in the same terms. The site includes a Grade B2 listed building at 6 Wellington Park (HB26/28/031 A), which the application material indicates is to be retained. The Botanic Inn and the main hotel are not themselves listed.
- LA04/2026/1495/DCA (conservation area consent) for demolition of the hotel complex and the Botanic Inn, to allow the 556-unit scheme.
A Proposal of Application Notice, LA04/2026/0849/PAN, received on 8 May 2026 and determined as acceptable on 4 June 2026, described a scheme of about 580 units. The later applications are for 556.
Timeline
The applications were received on 25 August 2026. The full application was validated on 28 September, and the listed building and conservation area consents on 25 August. Neighbours and consultees were notified in mid-October. On 17 November the Planning Committee listed a pre-emptive site visit, which was not a decision. As at 24 November the full application and listed building consent still showed as “Consultation Open”, and the conservation area consent as “Valid”. None had a decision or a committee date on the register.
What consultees have said
The register recorded 58 public comments on the full application, all objections, including a petition from “WP and SR Group” and an objection from Paula Bradshaw MLA. None were recorded in support. The petition’s signature total is not summarised on the register.
The council’s Conservation team objects to demolishing the Botanic Inn, saying the replacement would not make an equal or better contribution to the conservation area. Historic Environment Division (Historic Buildings) finds an adverse impact on listed buildings and their setting (BH1) and a failure to preserve or enhance the Malone Conservation Area (BH2). The council’s Urban Design officer has significant concerns about scale, height, massing and courtyard sunlight, and says the proposal would be contrary to policies SP5 and DES1–3. NI Water recommends refusal on foul sewer and water supply capacity, but may reconsider if the applicant engages as set out in its response. NIEA has asked for further ecological information. DfI Rivers says the site is not in the fluvial or coastal flood plain, but needs more drainage information. Responses from DfI Roads, Environmental Health and the Local Plan Team (Housing) were still outstanding.
The officer’s stated reasons
The letter of 19 November 2026 is correspondence with the agent, not a published committee report. It says there are fundamental problems that cannot be resolved following discussion, that the concerns were raised at pre-application discussion and at validation, and that no meaningful amendments have been made. The council is not accepting any further amendments or additional information and “will present the application to December committee with a recommendation to refuse.”
The reasons then in mind, which the letter says are “not exhaustive” and subject to change, are:
- The principle of demolition of the Botanic Inn, which in the council’s view makes a material contribution to the Conservation Area.
- The loss of an existing tourism asset, being the existing hotel.
- There is no longer a need for PBMSA.
- The scale, massing and design of the proposal and its impact on listed buildings and the Conservation Area.
- The impact on the residential amenity of surrounding residents through overlooking, dominance and overshadowing.
- The impact on the amenity of occupants through a lack of sunlight and daylight in the communal open space areas.
- Insufficient access arrangements to waste storage areas.
- Insufficient information to satisfy policy NH1, based on the NI Water and NIEA consultations.
On need, the letter says that although the Local Plan Team response is still outstanding, officers “expect concerns to be raised with the need for PBMSA.” That is an expectation in a letter, not a published Housing team response.
The policy context
The adopted plan is the Belfast Local Development Plan: Plan Strategy 2035 (May 2023). Policy HOU12 requires need to be shown for large-scale purpose-built managed student accommodation, and is supported by Supplementary Planning Guidance. Built heritage is assessed under BH1 (listed buildings, including setting) and BH2 (conservation areas). The officer’s concern about the loss of the hotel aligns with policy TLC2. Design, scale and massing are considered under SP5 and DES1–3. The officer’s letter also cites NH1 in the light of the NI Water and NIEA consultations.
What this means for applicants
The same tests arise on much smaller proposals, including an HMO, a change of use or a conversion in a conservation area.
Show need where policy requires it. If that case is not made, the principle of the development can fall even where the rest of the scheme has been carefully prepared.
Take heritage and conservation-area tests seriously from the outset. Demolition in a conservation area needs its own consent, and listed building consent is needed for works affecting a listed building or its setting. A building need not be listed for its loss to be resisted, if it contributes to the character of the area.
Engage on design early. Scale, height, massing, sunlight and neighbouring amenity are policy tests, not matters of taste.
Sort NI Water capacity and ecology information up front, before an application is submitted.
Use pre-application discussion, and act on it. The officer’s letter says the concerns were raised through a PAD and at validation, and that no meaningful amendments followed.
An open question
Officers now say there is no longer a need for further PBMSA in Belfast. That raises a fair question for the city: if student numbers fall in the years ahead, what happens to blocks that are left with vacant rooms? Would owners seek a change of use to general housing, co-living or short-term lets, and how should the planning system assess that? We would be interested to hear your view.
Next steps
The application is expected at the December Planning Committee. A December meeting is in the council’s published 2026 schedule, but as at 24 November 2026 no December agenda had been published, and no committee date is shown on the register. A hearing date should not be treated as confirmed until an agenda appears.
A recommendation is not a decision, and the reasons may change if remaining consultees respond. If permission were refused, an applicant may consider an appeal to the Planning Appeals Commission. The applications remain undetermined.
This article is general information, not advice on a particular site. No outcome can be guaranteed.
If you would like advice on a site, or you are considering purpose-built student accommodation, an HMO, a change of use or a conversion in a conservation area, please contact us through niplanningpermission.co.uk or call 028 9591 6888.
Sources
- LA04/2026/1538/F — full planning application, NI Planning Register
- LA04/2026/1539/LBC — listed building consent
- LA04/2026/1495/DCA — conservation area consent
- LA04/2026/0849/PAN — Proposal of Application Notice
- Officer letter to the agent, 19 November 2026 (document on the full application file; not a published committee report)
- Planning Committee, 17 November 2026 — pre-emptive site visit listed; not a decision
- Belfast City Council Planning Committee meetings, 2026
- Belfast Local Development Plan: Plan Strategy 2035 (adopted May 2023)
- PBMSA Supplementary Planning Guidance (Policy HOU12)
- Irish News, 21 November 2026 — source for the reported Mooney Hotel Group joint venture, which is not named on the Planning Register
Get planning advice
Send the site address and a line about your plans. A member of our planning team will reply, usually the same working day.