In Northern Ireland, full planning permission normally lasts five years from the date it is granted. If the development has not begun within that time, the permission expires. Outline planning permission works differently: an application for approval of the reserved matters must normally be made within three years, and the development must begin within five years of the outline grant or two years of the final reserved matters approval, whichever is later. A council can set a different period, so always read the conditions on your own decision notice.
This guide explains the law, what counts as starting work, and what to do if your permission is close to expiring. It is general information, not legal advice. For the time it takes to get a decision, see our separate guide on how long planning permission takes in Northern Ireland.
Full planning permission: the five-year rule
Section 61 of the Planning Act (Northern Ireland) 2011 says every planning permission is granted subject to a condition that the development must be begun within:
- five years of the date the permission is granted; or
- another period, longer or shorter, that the council considers appropriate having regard to the local development plan and other material considerations.
If a permission is granted without a time condition, the law deems it to have been granted subject to the five-year condition. In practice, most decision notices include a first condition along the lines of “The development hereby permitted shall be begun before the expiration of 5 years from the date of this permission”, with the reason given as section 61 of the 2011 Act.
The five-year rule does not apply to some types of permission, including outline permissions (covered below), permissions for a limited period, and retrospective permissions for development already carried out.
Outline planning permission: three years, then two
Section 62 of the 2011 Act deals with outline permission. Unless the council sets different periods, an outline permission is subject to conditions that:
- an application for approval of each reserved matter must be made within three years of the date of the outline grant; and
- the development must be begun by the later of five years from the outline grant, or two years from the final approval of the reserved matters.
The council can substitute different periods, so check the conditions. Missing the three-year deadline matters: under section 63, a reserved matters application made after the date set by the conditions is treated as not made in accordance with the permission. Our guide to outline planning permission in Northern Ireland explains outline applications in more detail.
What counts as “beginning” development?
Section 63 explains when development is taken to be begun. It is the earliest date on which any of the following operations comprised in the development begins to be carried out:
- for the erection of a building, any work of construction in the course of erecting the building;
- for alterations to a building, any work involved in the alterations; and
- for a change of use, the change of use itself.
Whether a particular operation is enough to count is a matter of fact and degree, and it can be disputed. Clearing a site or putting up a fence may not be treated as construction work comprised in the development.
Pre-commencement conditions
Some permissions include conditions that must be met before any work starts, for example approval of visibility splays, a landscaping scheme or drainage details. If work begins without those conditions being met, there is a risk that the start does not lawfully implement the permission. Leave time to discharge those conditions well before the expiry date. Our page on planning conditions explains how discharge works.
Once started, does the permission last for ever?
A permission that has been lawfully begun within the time limit does not then expire under section 61 or 62, even if the work pauses. However, any other conditions still have to be complied with, and long delays can create practical and legal questions. If a project has stalled, get advice on the position before restarting.
Can planning permission be extended or renewed?
There is no simple form to “extend” an expiring permission in Northern Ireland.
- Section 54 of the 2011 Act allows an application to vary conditions on a permission, but it cannot be used to extend the time for beginning development or for applying for reserved matters. It also cannot be used once the permission has expired without the development being begun.
- The usual route is a fresh planning application for the same development, often described as a “renewal”. It should be made well before the current permission expires.
A renewal is a new application. It is assessed against the planning policies that apply on the date of the decision, not the date of the original permission. That matters in the countryside, where several councils have adopted new Plan Strategies and PPS 21 no longer applies in those districts. A site approved several years ago may be assessed quite differently today. Read does PPS 21 still apply? for the background.
Practical checklist
- Find the decision notice and note the date of the grant and the time condition.
- For an outline permission, diarise the reserved matters deadline, not just the five-year date.
- List any pre-commencement conditions and allow time for the council to approve details.
- Keep dated evidence of the start on site, such as photographs, invoices and building control inspections.
- If you are buying a site with permission, check how long it has left to run.
Frequently asked questions
How long does full planning permission last in Northern Ireland?
Normally five years from the date of the grant, under section 61 of the Planning Act (Northern Ireland) 2011, unless the council has set a different period in a condition.
How long do I have to submit reserved matters?
Normally three years from the date of the outline permission, under section 62, unless the council has set a different period.
Can I get an extension of time on my planning permission?
Not by varying the time condition. Section 54 cannot be used to extend the time for starting development. The usual option is a fresh application before the permission expires.
Does digging foundations count as starting?
Work of construction in the course of erecting the building can count, but whether a particular operation is enough depends on the facts, and pre-commencement conditions must be dealt with first.
Does planning permission transfer when I sell the land?
Planning permission normally runs with the land rather than the owner, unless a condition says otherwise. A buyer takes on the same time limits and conditions.
How we can help
If your permission is close to expiring, or you are buying land with an existing approval, call our team on 028 9591 6888 or get in touch online. We can check the decision notice, the conditions and the policy that would apply to a renewal. See also our planning applications service.
Get planning advice
Send the site address and a line about your plans. A member of our planning team will reply, usually the same working day.