A new farm shed, or an extension to an existing agricultural building, is often assumed to be permitted development. In Northern Ireland some agricultural buildings are, but only if every test in the legislation is met. If any one of those tests is failed, you need to apply for planning permission before the work starts.
The legal source is the Planning (General Permitted Development) Order (Northern Ireland) 2015, Part 7, Class A, as it stands on the official legislation website. The Order has been amended several times, most recently in May 2026; that latest amendment concerns reverse vending machines, not agricultural buildings, but you should always check the current official text. nidirect advises you to ask the local planning office if you are unsure. Building regulations are a separate question.
What Class A actually permits
Class A of Part 7 permits, on agricultural land comprised in an agricultural unit, works for the erection, extension or alteration of a building, or any excavation or engineering operation, that are reasonably necessary for the purposes of agriculture within that unit.
Two phrases do a lot of the work. The land must be agricultural land in an agricultural unit, with the meanings assigned in the Order (which refer back to the Agriculture Act (Northern Ireland) 1949 for “agricultural land”). The works must be reasonably necessary for agriculture on that unit. A building that is not designed for agriculture, or that is in substance a new house, a farm diversification workshop, or a commercial store unconnected with the holding, is not what Class A is for.
Class A is also not the first agricultural building on the unit. If there is no existing agricultural building, a new shed is not permitted development under this class and a planning application is required.
The main limits
Development is not permitted by Class A if, among other things:
- it is on agricultural land less than 0.5 hectares in area (that area is calculated without taking into account any separate parcels of land)
- it consists of or includes the erection, extension or alteration of a dwelling
- a building, structure or works not designed for the purposes of agriculture is provided on the land
- the building or structure to be erected is the first agricultural building on the unit
- the nearest part of any building or structure so erected or extended is more than 75 metres from the nearest part of a group of principal farm buildings
- the nearest part of any building or structure so erected or extended is less than 75 metres from a dwellinghouse, other than a dwellinghouse of a person engaged in agricultural operations on that unit
- the ground area to be covered exceeds 500 square metres, calculated as described below
- the height of any part of the building, structure or works within 3 kilometres of the perimeter of an airport exceeds 3 metres, or 12 metres in any other case
- any part of the development is within 24 metres of the nearest part of a special road, or within 24 metres of the middle of a trunk or a first or second-class road, or 9 metres from the middle of other classes of road
The 500 square metre ground-area test is easy to underestimate. It is not simply the footprint of the new shed. Paragraph A.2(b) of the Order counts the ground area of the proposed development together with the ground area of any building (other than a dwellinghouse), or any works, structure, plant or machinery within the same unit, which is being provided under Class A or has been provided within the preceding two years, and any part of which is within 75 metres of the proposed development. A series of smaller sheds can, taken together, take you over the limit.
Other Part 7 classes, in brief
Part 7 also contains other classes that are not a substitute for Class A. Class B deals with the winning and working of minerals reasonably necessary for agricultural purposes on the unit, subject to its own limits and restoration conditions. Class C permits a means of access to a road only in defined circumstances, and not where a planning application is required for the development it would serve, or on a site of archaeological interest. Class D is a separate, tighter set of rights for anaerobic digestion of biomass produced on the unit. None of these classes should be stretched to cover a shed that fails Class A.
If permitted development does not apply
If the shed falls outside Class A, you should apply for planning permission. The application will be assessed against the development plan and other material considerations for that council area. In districts that have not yet adopted a Plan Strategy, countryside and agricultural policy in PPS 21 and related regional policy remains an important starting point. Where a council has adopted a Plan Strategy, that strategy is now the main policy framework. Landscape designations, access, slurry and dirty-water arrangements, and the effect on neighbours can all matter, depending on the site.
Applications for most councils are made through the NI Planning Portal. Mid Ulster District Council is the exception and runs its own online service.
A certificate of lawfulness is worth considering
If you believe the shed is permitted development, you can apply to the council for a Certificate of Lawful Use or Development for the proposed works. It is not compulsory, but it gives you a formal decision, which is often helpful when you later sell the holding, apply for a loan, or need to show a contractor or a neighbour that the works were lawful. A certificate is not the same as planning permission, and it is only as good as the facts and plans you put in. Our separate guide explains certificates of lawfulness in Northern Ireland.
Building control is a different approval
Even if planning permission is not required, building regulations may still apply. The two regimes are not interchangeable. Check the position with the council’s building control service before work starts.
How we can help
Our planning team is led by a Full Corporate Member of the Irish Planning Institute (MIPI). If you are unsure whether a farm shed or an agricultural extension falls within Class A, we can review the proposal against the current limits and advise whether a planning application or a certificate of lawfulness is the more appropriate route. Call NI Planning Permission on 028 9591 6888 or use our contact page.
Sources
- The Planning (General Permitted Development) Order (Northern Ireland) 2015, Part 7, Classes A to D, official text on legislation.gov.uk (checked 13 November 2026)
- The Planning (General Permitted Development) (Amendment) Order (Northern Ireland) 2026 (NISR 2026/80), which does not amend the agricultural building limits
- nidirect, Getting help with planning
- Department for Infrastructure, current planning legislation pages